Uhland Elementary School Overview

  • Hays CISD's 14th elementary school was approved by voters in the May 2017 bond election and construction began on the campus in June 2017. The campus will have a capacity of approximately 900 students and serve grades K - 5, offering state-of-the-art educational opportunities. 

    The 115,000 square-foot campus is projected to open in August 2018. The construction cost estimate is $28,750,000 ($250 per SF). The $33,925,000 total cost of project includes all necessary furniture, equipment, site infrastructure, architecture costs, and other fees. Any bond savings from a reduced cost of this project will be used to pay down existing debt, which returns the money to the taxpayers. 

    On December 11, 2017, the Board of Trustees voted to name the campus Uhland Elementary School in tribute to the Uhland School that was a centerpiece of the community during much of the 20th century. 

Uhland Elementary School Construction Updates

  • picture of elementary school construction

  • July 13, 2018 Construction Update (Uhland ES)

    Posted by David Bowe on 7/13/2018

    Uhland Elementary School construction update provided by Bartlett Cocke General Contractors. 

    Read the Update Here (PDF)

    Comments (-1)
  • July 6, 2018 Construction Update (Uhland ES)

    Posted by David Bowe on 7/6/2018

    Uhland Elementary School construction update provided by Bartlett Cocke General Contractors. 

    Read the Update Here (PDF)

    Comments (-1)
  • June 29, 2018 Construction Update (Uhland ES)

    Posted by David Bowe on 6/29/2018

    Uhland Elementary School construction update provided by Bartlett Cocke General Contractors. 

    Read the Update Here (PDF)

    Comments (-1)
  • June 22, 2018 Construction Update (Uhland ES)

    Posted by David Bowe on 6/22/2018

    Uhland Elementary School construction update provided by Bartlett Cocke General Contractors. 

    Read the Update Here (PDF)

    Comments (-1)
  • June 21, 2018 Special Construction Update (Uhland ES)

    Posted by David Bowe on 6/21/2018

    Here are some special interior pictures taken today by Uhland Elementary School Principal, Cynthia Vasquez. 

    construction picture of school library   construction picture of school gym  construction picture of school cafeteria  construction picture of school cafeteria  construction picture of interior school hallway

    Comments (-1)